Shipment lead time hedging and coordination in prefabricated construction supply chain
1
School of Management, Northwestern Polytechnical University, Xi’an, P.R. China
2
School of Management Engineering, Shandong Jianzhu University, Jinan, P.R. China
3
China Construction Eighth Engineering Division, Shanghai, P.R. China
* Corresponding author: 735972219@qq.com
Received:
29
September
2022
Accepted:
11
February
2024
This paper aims to coordinate a shipment lead time hedging (SLTH) problem between a building contractor and a logistics provider in the prefabricated construction supply chain (PCSC). In the PCSC, untimely (early or late) delivery of prefabs can lead to project time and cost overruns. To mitigate this challenge, the building contractor requires the logistics provider to reduce the shipping time variability, which is termed the SLTH strategy. While this benefits the building contractor, it also puts more investment and operational pressures on the logistics provider. To solve this conflict, we introduce a coordination mechanism which involves two terms: an SLTH level related cost term is charged by the logistics provider to the building contractor, and a constant transfer term is adopted to fairly allocate the system surplus. Three decentralized models are investigated: i.e., two Stackelberg game models with alternative decision-making sequences and an equal power model. Further comparative analysis and numerical studies reveal that our proposed coordination mechanism increases the SLTH level and ensures a win–win situation. Moreover, some interesting managerial implications are derived.
Mathematics Subject Classification: 90B05 / 90B06
Key words: Prefabricated construction / supply chain management / shipment lead time hedging / delivery performance / supply chain coordination
© The authors. Published by EDP Sciences, ROADEF, SMAI 2024
This is an Open Access article distributed under the terms of the Creative Commons Attribution License (https://creativecommons.org/licenses/by/4.0), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Current usage metrics show cumulative count of Article Views (full-text article views including HTML views, PDF and ePub downloads, according to the available data) and Abstracts Views on Vision4Press platform.
Data correspond to usage on the plateform after 2015. The current usage metrics is available 48-96 hours after online publication and is updated daily on week days.
Initial download of the metrics may take a while.