iBet uBet web content aggregator. Adding the entire web to your favor.
iBet uBet web content aggregator. Adding the entire web to your favor.



Link to original content: http://www.legislation.gov.uk/ukpga/1990/8/schedule/9/1991-02-01
Town and Country Planning Act 1990

Search Legislation

Town and Country Planning Act 1990

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 9

 Help about opening options

Version Superseded: 25/09/1991

Status:

Point in time view as at 01/02/1991. This version of this schedule contains provisions that are not valid for this point in time. Help about Status

Close

Status

Not valid for this point in time generally means that a provision was not in force for the point in time you have selected to view it on.

Changes to legislation:

Town and Country Planning Act 1990, SCHEDULE 9 is up to date with all changes known to be in force on or before 31 October 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

Section 102(8).

SCHEDULE 9 E+W Requirements relating to Discontinuance of Mineral Working

Modifications etc. (not altering text)

Orders requiring discontinuance of mineral workingE+W

1(1)If, having regard to the development plan and to any other material considerations, it appears to a mineral planning authority that it is expedient in the interests of the proper planning of their area (including the interests of amenity)—

(a)that any use of land for development consisting of the winning and working of minerals in, on or under the land should be discontinued, or that any conditions should be imposed on the continuance of that use of land; or

(b)that any buildings or works on land so used should be altered or removed; or

(c)that any plant or machinery used for the winning and working of minerals should be altered or removed,

the mineral planning authority may by order require the discontinuance of that use, or impose such conditions as may be specified in the order on the continuance of it or, as the case may be, require such steps as may be so specified to be taken for the alteration or removal of the buildings or works or plant or machinery.

(2)Subject to sub-paragraph (3), subsections (2) to (7) of section 102 and section 103 apply to orders under this paragraph as they apply to orders under section 102.

(3)In their application by virtue of sub-paragraph (2) subsections (2) to (7) of section 102 and section 103 shall have effect as if references to the local planning authority were references to the mineral planning authority.

2(1)Where development consisting of the winning and working of minerals is being carried out in, on or under any land, the conditions which an order under paragraph 1 may impose include a restoration condition.

(2)If such an order—

(a)includes a restoration condition, or

(b)a restoration condition has previously been imposed in relation to the land by virtue of any provision of this Act,

the order may also include any such aftercare condition as the mineral planning authority think fit.

(3)Paragraphs 2(3) to (9) and 3 to 6 of Schedule 5 shall apply in relation to an aftercare condition imposed under this paragraph as they apply in relation to such a condition imposed under paragraph 2 of that Schedule, but with the substitution for sub-paragraphs (1) and (2) of paragraph 3 of that Schedule of sub-paragraphs (4) and (5) below.

(4)In a case where—

(a)the use specified in the aftercare condition is a use for agriculture;

(b)the land was in use for agriculture immediately before development consisting of the winning and working of minerals began to be carried out in, on or under it, or had previously been used for agriculture and had not been used for any authorised purpose since its use for agriculture ceased; and

(c)the Minister has notified the mineral planning authority of the physical characteristics of the land when it was last used for agriculture,

the land is brought to the required standard when its physical characteristics are restored, so far as it is practicable to do so, to what they were when it was last used for agriculture.

(5)In any other case where the use specified in the aftercare condition is a use for agriculture, the land is brought to the required standard when it is reasonably fit for that use.

Prohibition of resumption of mineral workingE+W

3(1)Where it appears to the mineral planning authority—

(a)that development consisting of the winning and working of minerals has been carried out in, on or under any land; but

(b)that it has permanently ceased,

the mineral planning authority may by order—

(i)prohibit the resumption of such development; and

(ii)impose, in relation to the site, any such requirement as is specified in sub-paragraph (3).

(2)The mineral planning authority may assume that development consisting of the winning and working of minerals has permanently ceased only when—

(a)no such development has been carried out to any substantial extent anywhere in, on or under the site of which the land forms part for a period of at least two years; and

(b)it appears to the mineral planning authority, on the evidence available to them at the time when they make the order, that resumption of such development in, on or under the land is unlikely.

(3)The requirements mentioned in sub-paragraph (1) are—

(a)a requirement to alter or remove plant or machinery which was used for the purpose of the winning and working of minerals or for any purpose ancillary to that purpose;

(b)a requirement to take such steps as may be specified in the order, within such period as may be so specified, for the purpose of removing or alleviating any injury to amenity which has been caused by the winning and working of minerals, other than injury due to subsidence caused by underground mining operations;

(c)a requirement that any condition subject to which planning permission for development consisting of the winning and working of minerals was granted or which has been imposed by virtue of any provision of this Act shall be complied with; and

(d)a restoration condition.

(4)If—

(a)an order under this paragraph includes a restoration condition; or

(b)a restoration condition has previously been imposed in relation to the site by virtue of any provision of this Act,

the order under this paragraph may include any such aftercare condition as the mineral planning authority think fit.

(5)Paragraphs 2(3) to (9) and 3 to 6 of Schedule 5 apply in relation to an aftercare condition imposed under this paragraph as they apply to such a condition imposed under paragraph 2 of this Schedule.

4(1)An order under paragraph 3 shall not take effect unless it is confirmed by the Secretary of State, either without modification or subject to such modifications as he considers expedient.

(2)Where a mineral planning authority submit such an order to the Secretary of State for his confirmation under this paragraph, the authority shall serve notice of the order—

(a)on any person who is an owner or occupier of any of the land to which the order relates, and

(b)on any other person who in their opinion will be affected by it.

(3)The notice shall specify the period within which any person on whom the notice is served may require the Secretary of State to give him an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for that purpose.

(4)If within that period such a person so requires, before the Secretary of State confirms the order he shall give such an opportunity both to him and to the mineral planning authority.

(5)The period referred to in sub-paragraph (3) must not be less than 28 days from the service of the notice.

(6)Where an order under paragraph 3 has been confirmed by the Secretary of State, the mineral planning authority shall serve a copy of the order on every person who was entitled to be served with notice under sub-paragraph (2).

(7)When an order under paragraph 3 takes effect any planning permission for the development to which the order relates shall cease to have effect.

(8)Sub-paragraph (7) is without prejudice to the power of the mineral planning authority, on revoking the order, to make a further grant of planning permission for development consisting of the winning and working of minerals.

Orders after suspension of winning and working of mineralsE+W

5(1)Where it appears to the mineral planning authority—

(a)that development consisting of the winning and working of minerals has been carried out in, on or under any land; but

(b)that it has been temporarily suspended,

the mineral planning authority may by order require that steps shall be taken for the protection of the environment.

(2)An order under sub-paragraph (1) is in this Act referred to as a “suspension order”.

(3)The mineral planning authority may assume that development consisting of the winning and working of minerals has been temporarily suspended only when—

(a)no such development has been carried out to any substantial extent anywhere in, on or under the site of which the land forms part for a period of at least 12 months; but

(b)it appears to the mineral planning authority, on the evidence available to them at the time when they make the order, that a resumption of such development in, on or under the land is likely.

(4)In this Act “steps for the protection of the environment” means steps for the purpose—

(a)of preserving the amenities of the area in which the land in, on or under which the development was carried out is situated during the period while operations for the winning and working of minerals in, on or under it are suspended;

(b)of protecting that area from damage during that period; or

(c)of preventing any deterioration in the condition of the land during that period.

(5)A suspension order shall specify a period, commencing with the date on which it is to take effect, within which any required step for the protection of the environment is to be taken and may specify different periods for the taking of different steps.

Supplementary suspension ordersE+W

6(1)At any time when a suspension order is in operation the mineral planning authority may by order direct—E+W

(a)that steps for the protection of the environment shall be taken in addition to or in substitution for any of the steps which the suspension order or a previous order under this sub-paragraph specified as required to be taken; or

(b)that the suspension order or any order under this sub-paragraph shall cease to have effect.

(2)An order under sub-paragraph (1) is in this Act referred to as a “supplementary suspension order”.

Confirmation and coming into operation of suspension ordersE+W

7(1)Subject to sub-paragraph (2), a suspension order or a supplementary suspension order shall not take effect unless it is confirmed by the Secretary of State, either without modification or subject to such modifications as he considers expedient.E+W

(2)A supplementary suspension order revoking a suspension order or a previous supplementary suspension order and not requiring that any fresh step shall be taken for the protection of the environment shall take effect without confirmation.

(3)Sub-paragraphs (2) to (5) of paragraph 4 shall have effect in relation to a suspension order or supplementary suspension order submitted to the Secretary of State for his confirmation as they have effect in relation to an order submitted to him for his confirmation under that paragraph.

(4)Where a suspension order or supplementary suspension order has been confirmed by the Secretary of State, the mineral planning authority shall serve a copy of the order on every person who was entitled to be served with notice of the order by virtue of sub-paragraph (3).

Registration of suspension orders as local land chargesE+W

8E+WA suspension order or a supplementary suspension order shall be a local land charge.

Review of suspension ordersE+W

9(1)It shall be the duty of a mineral planning authority—E+W

(a)to undertake in accordance with the following provisions of this paragraph reviews of suspension orders and supplementary suspension orders which are in operation in their area; and

(b)to determine whether they should make in relation to any land to which a suspension order or supplementary suspension order applies—

(i)an order under paragraph 3; or

(ii)a supplementary suspension order.

(2)The first review of a suspension order shall be undertaken not more than five years from the date on which the order takes effect.

(3)Each subsequent review shall be undertaken not more than five years after the previous review.

(4)If a supplementary suspension order is in operation for any part of the area for which a suspension order is in operation, they shall be reviewed together.

(5)If a mineral planning authority have made a supplementary suspension order which requires the taking of steps for the protection of the environment in substitution for all the steps required to be taken by a previous suspension order or supplementary suspension order, the authority shall undertake reviews of the supplementary suspension order in accordance with sub-paragraphs (6) and (7).

(6)The first review shall be undertaken not more than five years from the date on which the order takes effect.

(7)Each subsequent review shall be undertaken not more than five years after the previous review.

(8)The duties to undertake reviews imposed by this paragraph are in addition to and not in substitution for the duties imposed by section 105.

Resumption of mineral working after suspension orderE+W

10(1)Subject to sub-paragraph (2), nothing in a suspension order or a supplementary suspension order shall prevent the recommencement of development consisting of the winning and working of minerals in, on or under the land in relation to which the order has effect.

(2)No person shall recommence such development without first giving the mineral planning authority notice of his intention to do so.

(3)A notice under sub-paragraph (2) shall specify the date on which the person giving the notice intends to recommence development consisting of the winning and working of minerals.

(4)The mineral planning authority shall revoke the order if development consisting of the winning and working of minerals has recommenced to a substantial extent in, on or under the land in relation to which the order has effect.

(5)If the authority do not revoke the order before the end of the period of two months from the date specified in the notice under sub-paragraph (2), the person who gave that notice may apply to the Secretary of State for the revocation of the order.

(6)Notice of an application under sub-paragraph (5) shall be given by the applicant to the mineral planning authority.

(7)If he is required to do so by the person who gave the notice or by the mineral planning authority, the Secretary of State shall, before deciding whether to revoke the order, give him and the mineral planning authority an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.

(8)If the Secretary of State is satisfied that development consisting of the winning and working of minerals in, on or under the land has recommenced to a substantial extent, he shall revoke the order.

(9)If the Secretary of State revokes an order by virtue of sub-paragraph (8), he shall give notice of its revocation—

(a)to the person who applied to him for the revocation, and

(b)to the mineral planning authority.

Default powers of Secretary of StateE+W

11(1)If it appears to the Secretary of State to be expedient that any order under paragraph 1, 3, 5 or 6 should be made, he may himself make such an order.E+W

(2)Such an order which is made by the Secretary of State shall have the same effect as if it had been made by the mineral planning authority and confirmed by the Secretary of State.

(3)The Secretary of State shall not make such an order without consulting the mineral planning authority.

(4)Where the Secretary of State proposes to make an order under paragraph 1 he shall serve a notice of the proposal on the mineral planning authority.

(5)The notice shall specify the period (which must not be less than 28 days from the date of its service) within which the authority may require an opportunity of appearing before and being heard by a person appointed by the Secretary of State for the purpose.

(6)If within that period the authority so require, before the Secretary of State makes the order he shall give the authority such an opportunity.

(7)The provisions of this Schedule and of any regulations made under this Act with respect to the procedure to be followed in connection with the submission by the mineral planning authority of any order to which sub-paragraph (1) applies, its confirmation by the Secretary of State and the service of copies of it as confirmed shall have effect, subject to any necessary modifications, in relation to any proposal by the Secretary of State to make such an order, its making by him and the service of copies of it.

Modifications etc. (not altering text)

C2Sch. 9 para. 11 : power to apply conferred (10.11.1993) by 1993 c. 28, s. 171(4)(a); S.I. 1993/2762, art. 3

Valid from 25/09/1991

[F1 InterpretationE+W

Textual Amendments

F212E+WIn this Schedule any reference to a mineral planning authority shall be construed, in relation to the exercise of functions with respect to the depositing of refuse or waste materials (other than mineral waste), as a reference to the authority entitled to discharge such functions.]

Textual Amendments

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources