Town and Country Planning Act 1990, Paragraph 1 is up to date with all changes known to be in force on or before 31 October 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Act (including any effects on those provisions):
[1(1)Every existing plan which relates to any part of Wales shall continue in force on and after 1st April 1996.E+W
(2)When a unitary development plan has become fully operative for the area of a local planning authority in Wales—
(a)any existing plan which is for the time being in force; and
(b)any interim plan,
shall cease to have effect in respect of its plan area to the extent that it is comprised in the area of that local planning authority.
(3)Any existing plan or interim plan shall, while it continues in force in respect of the area, or part of the area, of any local planning authority in Wales, be treated for the purposes of—
(a)this Act,
(b)any other enactment relating to town and country planning,
(c) the M1 Land Compensation Act 1961, and
(d) the M2 Highways Act 1980,
as being, or as being comprised in, the development plan in respect of that area or, as the case may be, that part of that area.
(4)Sub-paragraphs (1) to (3) have effect subject to the provisions of this Part of this Schedule and the 1994 Act transitional provisions.
(5)In this paragraph—
“ the 1994 Act transitional provisions ” means the provisions of Part III of Schedule 5 to the Local Government (Wales) Act 1994;
“ existing plan ” means a—
structure plan;
local plan; or
old development plan,
to the extent that it was in force in respect of any area in Wales immediately before 1st April 1996 (and includes any alteration made to, or replacement of, the plan after that date under the 1994 Act transitional provisions);
“ interim plan ” means any modified plan (within the meaning of the 1994 Act transitional provisions) which comes into force in respect of any area in Wales on or after 1st April 1996 under those provisions;
“ old development plan ” means any plan which was in force immediately before 1st April 1996 by virtue of Schedule 7 to the M3 Town and Country Planning Act 1971 and Part III of this Schedule; and
“ plan area ”, in relation to an existing plan or interim plan, means the area in respect of which it was in force immediately before 1st April 1996 or, as the case may be, comes into force on or after that date. ]
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: